What permits do you need to install solar panels?

Date Published

What permits are needed to install solar panels?

Installing solar panels involves a number of permits and procedures, both before and after the installation, that you need to know about. The paperwork is also spread across different administrations (local, regional and national). So that you don't get lost in this bureaucratic pool, in this article we list the permits you need to install solar panels.

List of permits needed to install solar panels.

The permits and contracts required can vary depending on the type of installation and the town where it is carried out. The main ones to bear in mind are:

  • Technical report or design project
  • Grid access and connection permits
  • Building permit
  • Prior administrative authorisation and construction permit
  • Environmental authorisation
  • Installation/end-of-works certificate
  • Operating authorisation
  • Initial inspection
  • Registration of the self-consumption installation
  • Access contract
  • Energy supply contract for auxiliary services
  • Surplus compensation contract
  • Representation contract

Below we describe each of them, grouping them by when they are needed.

Permits before installing the solar panels.

Technical report or design project.

Every installation, whether in a home or in industry, requires a prior design. Depending on its capacity, as we have already told you in previous articles on our blog, you will need a technical report (up to 10 kW) or a project (if it exceeds 10 kW).

Grid access and connection permits.

These are required if the solar installation is outside urban land. They are also needed if it exceeds 15 kWn or if the installation feeds surplus into the grid, even within urban land. For installations without surplus, you only need to request the Universal Self-Consumption Code (CAU).

Building permit.

Most autonomous communities have removed this requirement, but it is always advisable to ask the town hall where the installation is carried out, as it may ask for certain information and for payment of the Construction and Works Tax (ICIO) and the urban planning services fee.

Prior administrative authorisation and construction permit.

Administrative authorisation is only mandatory for photovoltaic installations of more than 100 kWp.

Environmental authorisation.

As in the previous case, it is not usually necessary for solar installations under 100 kWp, but this depends on the environmental regulations of each autonomous community, so we recommend consulting the relevant authority in each case.

Photo03 1536x1021

Permits after installing the solar panels.

Installation/end-of-works certificate.

This document certifies that the work has been carried out correctly. If a technical report was submitted (installations under 10 kW), it can be issued by an electrician, and for projects (over 10 kW) it must be issued by a senior engineer with competence in electricity. It must be submitted to the town hall or the autonomous community.

Operating authorisation.

The autonomous community grants the authorisation to operate for the production, transmission or distribution of electricity. This authorisation is only needed for projects that have submitted the administrative authorisation or a design project, that is, it is not needed for small photovoltaic self-consumption installations.

Initial inspection.

Some autonomous communities may require an initial inspection by an Authorised Control Body (OCA). This is not usually the case for small installations (under 10 kW) unless they are in special environments, such as places open to the public, damp premises, and so on. In any case, we recommend consulting the autonomous community concerned.

Legalising the solar panel installation.

After the installation is finished it must be legalised, which requires the following contracts.

Access contract.

This is the contract with the electricity company. If you already had one, you need to notify the new photovoltaic self-consumption arrangement.

Energy supply contract for auxiliary services.

Only needed for installations that feed in surplus if more than 1% of the energy generated is exceeded, and it allows the installation to operate.

Surplus compensation contract.

For installations with surplus, a contract must be drawn up between producer and consumer, setting out conditions such as prices, allocation (individual or collective), and so on.

Representation contract.

Only needed for photovoltaic self-consumption with surplus that is not covered by a compensation scheme, in which case conventional generator rules will apply and this contract must be signed.

How to handle all the permits needed to install solar panels.

Installation companies usually take care of most permits and authorisations, since they have experience in handling documentation and processing it. Remember that the administrative side is often one of the main reasons installations are delayed. That is why it is important for these companies to be able to manage all the documentation efficiently and submit each of the relevant procedures on time and in the right form. Having a good internal management system that integrates the administrative and technical sides of photovoltaic projects is a solution that lets them offer a better service to their customers.