# When does a photovoltaic installation need a project?

> When a photovoltaic installation needs an electrical project and what the regulations say: we explain what each case requires at registration.

Published: 2023-01-16

Complying with regulations when carrying out photovoltaic installations is a fundamental part of the registration process. In this article we want to talk to you about the electrical project and the technical report. Are they the same thing? When is an electrical project needed for a photovoltaic installation? When is it not needed?

## Photovoltaic installation project: what is it?

When we talk about electrical installations (such as solar photovoltaic ones), **the installation project is the technical document that defines all the characteristics the electrical installation must have**. The project is not a single document, but is made up of the descriptive report of the installation, all the necessary drawings, the documents with all the calculations that justify the cabling and protections to be used, the budget and the conditions of the materials to be used. These documents must be **prepared and signed by an engineer or technical engineer**, so that all current regulations are met. In short, the project contains all the information needed for a low-voltage electricity generation installation that will be used for own consumption (appliances, lighting, small machinery, etc.).

## When is a project needed?

Not all solar panel installations need an installation project. To know in which cases one is required, you must consult the **Low Voltage Electrotechnical Regulation (REBT)**, specifically **point 3 of ITC-BT 04**. That point of the technical instruction details all the cases in which an installation project is required, including the following one (which is the one that interests us for photovoltaic self-consumption installations): *Low-voltage generating installations of 10 kW or more.* Self-consumption installations, being electricity generation installations, fall under that point. Therefore, **if the installation is over 10 kW, an electrical installation project prepared and signed by a competent technician is required**. If the installation is under 10 kW, a descriptive technical report (MTD) of the installation will be enough. Another case in which a project will be required is when the grid connection is at high voltage (rather than low voltage). In these cases an MTD will not be enough either; we will need an engineer to design and sign off the installation.

### At what point is the installation project needed?

Usually the design of the installation is one of the first steps, since it contains important information for making the sales proposal (size, number of panels, installation cost, etc.).

![Photo05 1536x1085](https://wattwin.com/api/media/file/site-site-blog-permisos-instalacion-fotovoltaica-2-foto05-1536x1085.jpg?prefix=media)

## Are there differences between autonomous communities?

There may be some confusion at this point because processing photovoltaic self-consumption installations involves procedures with authorities at local, regional and national level, depending on the installation's capacity, the self-consumption type, the type of connection, whether it is an individual or collective installation, etc. As for whether an electrical installation project is needed, **there are no differences at the autonomous community level, since the Low Voltage Electrotechnical Regulation applies throughout the country.** The project must be submitted to the autonomous community's regional ministry of industry when filing the electrical certificate, as a step prior to signing a contract with the area's electricity distributor. This step is carried out once the installation is already in place. Therefore, as we mentioned earlier, whether a project or a report is needed will depend on the type of grid connection and the installation's capacity:

- A technical design report will be enough: if the connection is low voltage and the capacity is 10 kW or less, which must be prepared by an authorised installation company.
- **A technical project will be required: if the connection is low voltage with a capacity above 10 kW**, which must be drafted and signed by a qualified technician competent in electrical projects. The same applies to high-voltage grid connections (for any installation capacity).

Where differences between autonomous communities can appear is in steps after the installation design, such as applying for environmental and public utility authorisations, or applying for prior administrative authorisation and construction authorisation, both of which are regional responsibilities. A building permit will also be required, which depends on the town council where the installation is located, and in this respect each one may also show slight differences in procedure and the documentation to be submitted.

## Need to speed up the management of your projects' documentation?

As we have seen, projects must include various documentation (drawings, budget, materials, descriptive report, etc.). Having the right software tool can save you many hours preparing all this documentation and shorten your turnaround times. If you want to find out how **Wattwin** can help you, get in touch with us.